Pre-Operation Inspection & Preparation
Power and Air Supply
Power Switch Check: Ensure the rear power switch is set to "1". Confirm the machine indicator light is on.
Airflow Meter Reset: Confirm the airflow meter is at its lowest setting to protect the material tray.
Oxygen Concentrator: Turn on the oxygen concentrator and wait 10 minutes for the airflow to stabilize.
Airflow Adjustment: Adjust the airflow to the recommended range of 0.5–0.6.
Temperature Control: Check the temperature gauge; the recommended setting is 40°C.
Components & Materials
Tray & Build Block: Ensure both are securely locked and all screws are tight.
Material Inspection: Check the bottled material to ensure it is in a liquid state, especially if the ambient room temperature is low.
Pre-Run Inspection
Build Block Security: Re-confirm that the build block is tightened and no screws are loose.
Tray Inspection: Ensure there are no residues or debris inside the tray. The material should be transparent and clear (if it appears cloudy, continue heating and wait).
File Import
- Parameter Verification: After importing the file, verify the total layers, layer thickness, curing time, and estimated print time.
Post-Printing
- Completion Protocol: Remove the workpiece using a scraper. Clean and inspect the build block to ensure no debris remains.